No possibility to change cost center in asset capitalized

Former Member
0 Kudos

Hi,

I'm working on ECC 6.0 and I've a problem to change a cost center in an asset capitalized.

Is it possible to change the cost center for posting the internal organizational transfer?

Tks for help!

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member375980
Active Contributor
0 Kudos

If the asset is linked to investment measure the cost center in

asset master data is blocked for change. You can only change it via tthe cost center in the WBS element or internal order.