on 09-16-2008 2:37 PM
Hi all,
When creating confirmation for a header order with transaction co11n for a certain operation, which is marked as first operation, the system creates confirmation for all suborders operations which should not happen. This happens on ECC 6.0. presumely because of FM MILL_OC_LAST_OPERATION which was newly implemented.
Has anyone any idea?
Is this a customizing issue or can be solved within an user exit? If programming needed what do you think has to be done?
Thanks in advance for any advices,
Florin
EG: header order 700403 with operation 10, 20, 30, 40. Suborders 700401 and 700402 with the same number of operations. When confirming header order with transaction co11n all suboders operation are confirmed although, the confirmation of the header order was done for operation 10 (marked as first operation).
Hello,
If the 1st operation is defined as Milestone operation , then change control key and try.In collective order When you confirm at operation level, you can confirm operations for all orders as long as you work with milestone operations.
Regards
Pradeep Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
If the 1st operation is defined as Milestone operation , then change control key and try.In collective order When you confirm at operation level, you can confirm operations for all orders as long as you work with milestone operations.
Regards
Pradeep Kumar
Hi,
thanks for the quick reply. Can you write me pls where can I change the control key and subsequently the milestone operation?
Thanks ,
Florin