Hi,
I have created a Personal in PA30, but when I try to assign it to a project in CJ02, I donu2019t found it!!!
I listened that we can do transfer between HR and PS but I donu2019t know how!!!
Can any one suggest?
Thank you in advance
Best regards
Mustapha
Still, I am not clear about your requirement,
HR and PS integration Process:
1) Create Project Definition
2) Assign you project definition to your Enterprise key components like Company code, Business area, and Controlling Area.
3) Assign the Newly created PS related WBS elements in IT 0015 or IT 2002.
and finally Check in ASSOB_HR table
Regards
Suresh.KK