on 09-16-2008 1:27 PM
hi guys,
I have schedule agreement with JIT delivery schedule line, need to map relationship between delivery note and JIT schedule line item. Need to transfer information on schedule line to delivery note. Do you have any idea?
thank you in advance!
Hi,
In VA32, in JIT tab enter the date, time and and quantity and save the document.
in VL10E you can deliver for the required date.
Chetan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First you have to determine what your schedule line is.
You then check that this is assigned a correct MRP type and movement.
Then you have to determine what your delivery type is.
Then check your copy control in Tx VBX1
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.