All,

In my scenario I am doing MTO backflush using MRP generated Planned order.Since MRP assigns first production version to planned order by default.But at the time of backflush I want to change it maually.In MTO backflush how to do it??

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI

its better to change the Prod version in change planned order,MD12

-ashok

former_member189817
Active Contributor
0 Kudos

Yes !! But Other than tha any other way to change it at the time of MFBF.

Former Member
0 Kudos

HI

since its MTO , there is no option...in MFBF.

-ashok