Here I had a problem that is
I want to create a STO(Stock Transfer Order) while changing the status of my KANBAN to EMPTY , This transfer is for CROSS PLANT.
Which Replinishment Strategy I need to use in my control cycle?
Krishna MOhan.
Hi,
Sorry i have given wrong information.
First in the material master select the special procurement key in the receiving plant.
in the control cycle select the replenishment type as "stock transfer"
strategy as "Working with direct transfer posting".
For this strategy in the configuration select the "from Dif plant" check box in the configuration
So once create control cycle and select the replenishment type as "stock transfer" with strategy
" Working with direct transfer posting" then system ask issuing plant and its storage location.
Try to do the above same configuration and execute.
Regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
U can use stock transfer replenishment strategy only
Just enter the cross plant storage location and execute
Regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.