on 09-16-2008 8:11 AM
Hi,
I have done some changes in application table (Y - table) through SM30.
Now I want to transport these changes to production.
Can anybody please tell me what is the procedure to transport these changes to production.
Thank you,
Warm Regards,
Mayur
Hi,
I have a problem, I don´t know to transport a table from development to production
I need help me , thanks.
bye
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Select all the entries in table over SE16 or SM30 and then go to menu table-entries and entries transport.
The system will ask you for transport then.
1. For not generating request (TR):
Use T.code:SCC4, Select your development client and double click; system will take to new screen.
Now check changes and transport for client specifics Tab and select automatic recording of changes and save.
2. The following T.codes are used for creation, release and transport the TR.
SCC4: client setting done for generating TR.
SE01/SE09: To release the TR,
SCC1: Transport TR from Client to Client,
STMS: Transport TR from Server to Server
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.