on 09-16-2008 6:40 AM
Hi Friends
Please provide me with the configuration steps for Factory Calendar.
Jade
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please follow as below,
1.Go to SCAL transaction
2.there will be three options.
Click first public holidays and go in change mode.
Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)
3.Now click Holiday calendar and go in change mode.
Click create and give holdiay cal id and description.
Click assign public holiday and add your holidays one by one and save
Now holiday cal is created.
4.Now come out and choose fact calendar and go in change modeClick create and give Factory calendar id and description, and validity period.Give the holiday calendar ID.
If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define)
and save.
5.You have to assign factory calendar to PLANT
Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT.
Hope this help.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.