PR Configuration ERROR

Former Member
0 Kudos

Dear All,

I have followed all proper steps, but still is giving following error

Check Release Classes ( See Long Text )

Please Help me out.

Thanks & Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check Release class which you are using, you have to use only one release class which is already defined you are not supposed to two release classes.

Regards

Ravi shankar.

Answers (5)

Answers (5)

Former Member
0 Kudos

Dear,

Go with below process and compare your process with below detail.

Business Process: -

Purchase requisition is creating PPA person than PPA head release this purchase requisition.

Process of Release Strategy: -

Procedure with Classification: -

Edit Characteristics: -

For implement release strategy for purchase requisition you have to create Characteristics - CT04.

For Example: -

Suppose you want to create release strategy for purchase requisition document type wise. So you create characteristics for purchase requisition document type with CT04 - document_type.

Edit Classes: -

After creation of characteristics, Create Class - CL01 for release strategy of purchase requisition.

For Example: -

Create class for purchase requisition like: Release_PR

Set Up Procedure with Classification: -

In this node you can maintain following details.

Release Group

Release Codes

Release Indicator

Release Strategies

Now we see above details in briefly

Release Group: -

You can maintain release group in this node. This permits the multiple usage of the same release strategy key

For example: - Create 01 - Release Group for purchase requisition release strategy and assign your class of release strategy.

Release Codes: -

You can maintain release code against release group with this node.

For example: - Create release code 01 - PPA Head against release group 01 - release group.

Release Indicator: -

You can create release indicator with this node, like blocked, in process, Release.

For example: - Create two indicators, Like X - Blocked, 9 - Release.

Release Strategy: -

After click on this node you can see four different step for release strategy of purchase requisition.

Release prerequisites, Release status, Classification, Release simulation.

First off all maintain your release code in Release code tab. Than done some bellow settings.

Release prerequisites: -

Click on release prerequisites tab, change your required changes and click on continue button.

Release Status: -

In this node you can set your path of release strategy.

For example: - you want to create release strategy like when PPA head tick on release indicator at that time purchase requisition made release. So you can set it via release status.

Classification: -

In this node you have to enter value of characteristics.

For example: - enter NB - standard pr for document_type.

Note: - Before enter value in Classification, You have to maintain value in characteristics - CT04 in value tab.

Release simulation: -

Check release simulation for release strategy.

After done this process, Create purchase requisition for document type NB - Standard PR.

At the time of check release strategy will be implemented in your purchase requisition.

You can release it via ME54N. List of purchase requisition release with ME55.

Regards,

Mahesh Wagh

Former Member
0 Kudos

Hi,

In the PR Release Procedure check the Release Classes.

It should be same as the Class which you defined in CL02.

Check Release group tab whether you are entering the proper entry.

If you define multiple Release Group then the Release Class should be entered single Rel class.

rgds

GSC

former_member192897
Active Contributor
0 Kudos

Please Click on see Long Texts. You will find the Solution in this itself..

Procedure : Assign the release groups that were created for overall releas to one release class only. Assign the release groups that were not created for overall release to a different release class.

Regards,

Ashok

Former Member
0 Kudos

Hi,

U check the release procedure properly,

Class Cl02, u assigned all characterstics properly,

then u check release pre requisites & release statuses properly, classification.

Pandari

Former Member
0 Kudos

Check release classes ....