Please help on the below issue:-
We are carrying settlement of order (Period end activities ) for CO88 . We are getting the following error complete allocation structure GA.
Please guide us.
Regards
Srinivas
Hi,
Go to Allocation structure and maintain the Source and Settlement cost element for various cost groups in the structure.
And maintain this Allocation Structure in the settlement profile for your Production/Process orders.
Regards
Balaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Maintain the Allocation Structure for Settlement of Production Order like Source, Assesment Cost Element, Settlement Cost Element and also maintain Settlement Profiles.
Regards
Shammi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.