on 09-16-2008 4:34 AM
Hi
If i hv a matl which is assigned to a WBS element (Project). All PR, PO, MIGO cycles r over. Now it is avl in MMBE as Project Stock as 10 Nos.
Now i want to reject 2 nos n return to vendor. HOW TO DO THIS? EXPLAIN WITH STPS IN DETAIL
Also is this possible to transfer the project stock to diff str loc???
Regards
Ram
Hi,
You also use movment type 301 for project stock tranfer storage to storage.
MIGO- Transfer Posting -Others-Mov Type-301
Enter Material Code
Enter Plant Code
Enter storage location ( From ) - 0011 ( Project stock) & Destination - storage location -0010 ( store)
Enter - Unit of entry ( Qty ) >> check & post.
Thaks & Rgds
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Stock trasfer storage lotation to storage location.
T Code- MIGO
Mov Type - 311
Thanks & Rgds,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I am also talking about project stock.
MIGO- Transfer Posting -Others-Mov Type-311
>>Enter Material Code
>>Enter Plant Code
>>Enter storage location ( From ) - 0011 ( Project stock) & Destination - storage location -0010 ( store)
Enter - Unit of entry ( Qty ) >> check & post.
Thaks & Rgds
Rajesh
Hi,
I am also talking about project stock.
MIGO- Transfer Posting -Others-Mov Type-311
>>Enter Material Code
>>Enter Plant Code
>>Enter storage location ( From ) - 0011 ( Project stock) & Destination - storage location -0010 ( store)
Enter - Unit of entry ( Qty ) >> check & post.
Thaks & Rgds
Rajesh
Hi Experts
Any solution for me.
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.