on 09-15-2008 1:57 PM
Hi,
we have 2 different system-lines each with a Enterprise Portal, Java Stack and ABAP System for a Development, Quality and Production-System using BI 7.0 on SP15.
Example for Production:
EP 1 -> WAS 1 -> ABAP 1
EP 2 -> WAS 2 -> ABAP 2
For Maintenance reasons we want to have only one Portal and one Java Stack working with the two ABAP-Systems-Lines.
Target environment:
EP new -> WAS new -> ABAP 1
-> ABAP 2
As i heard, BI 7.0 could only work with one dedicated ABAP System. I found no documentation or notes for such a limitation.
It is true ? Where can i found informations about the installation szenarios ?
Thanks for help.
Regard
Jürgen
Hi,
Please check whether the notes 917950 and 888687 are helpful to you.
Award points if useful.
Thank you.
Regards
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
24 | |
11 | |
9 | |
7 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.