on 09-15-2008 12:27 PM
Hi,
I noticed below 2 fields in OPUK for Project Definition (Project Systems > Structures > Operative Structures > Work Breakdown Structures (WBS) > Define Field Selection for Work Breakdown Structures). Could you help to advise where they are located in the Project Definition master record?
No project stock PROJ_BEST_NOBEST
Non-valuated stock PROJ_BEST_UNBWRT
Also, could you advise if I can add additional fields for defining whether to display or not (suppress, mandatory, etc) for Project Definition aside from those 53 default fields?
Thanks!
Regards,
Vivian
Hi,
You will find these two fields in OPUJ (Field selection for Project definition). You can make these two fields mandatory or hide here.
Hope this will help you.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The fields for project stock are those in the project defination control data tab (radio buttons).
I doubt if you can add in to the list.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.