on 09-15-2008 12:08 PM
Dear Gurus,
Some of our projects allowed cost assignments even when the budget is not sufficient.
I tried to reconstruct the availability control. The message says the "Availability Control already active."
We have a situation as below..
Overall budget - 30,000/-
Overall Commitments - 10,000/-
Overall Actual Costs - 22,000/-
Available Budget - (2,000/-) negative value.
What could be the reasons for such situation?? Iam unable to simulate this in test server..
How to resolve this..
thank you
KAP
hi,
Encountered this problem too.
We allocated budget to WBS (with currency = USD), based on transaction currency eg. USD.
Then, put in our own checks (user exits) to check availability in transaction currency(eg. USD).
So we minimised the fluctuation of the exchanges rates at the different stages (GR, IV etc).
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi KAP,
Instead of giving ++++ for all the transactions in the tolerance limit, give separate line item for each and every transaction.
This will not solve your problem. But just give a try and this does not costs you anything.
Sometimes SAP acts wierd.
Regards
Srinivasan Desingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Srinivasan,
I have tried this already. There was no change.
Now i have some more info which can potentially provide some clues.
After checking the projects which had this over run with available budget negative, we observed some of the projects were having POs both in USD and INR.
Is the exchange rate covered under availability control??
Maybe the PO was created using USD @ some rate and the GR/IR at different rate.. Can this happen??
And what is Program Budget?? (Value Type 47) Does that have any impact on availability control??
regards
KAP
Hi,
I also encountered the same thing,
It can happen that PO value has suppose exchange rate of 50.75 INR, whereas your GR has value of 68.15 INR, because of your current exchange rate.This increased your GR value more than PO and might be above your budget, which lead to available budget as Negative.
Now question is why AVAC didnt check while GR.
As a standard SAP Practice, AVAC will not check commitment against budget, while creation of GR.
Refer SAP Note: 46209.
If you want AVAC to check during GR, Implement SAP note- 696362.
Implement the note.
Thanks,
Nitin
Check out ur tolerance limits for Budget
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.