cancel
Showing results for 
Search instead for 
Did you mean: 

Actual work in maintenance order

Former Member
0 Kudos

Hi,experts,

In maintenance order,suppose 3 persons can complete a work in 4 hrs, so I m entering in "work" field as 4 ,"unit" as H and "Number" as 3 , now my doubt is about planned cost for the labour, planned cost for labour is coming only for 4 hrs, but in my view it should come for 3x4=12 hrs .means say , rate for 1 hr =INR 100/- so planned cost for labour should come INR 1200/- , while it is coming only INR400/-,Also, in IW41/IW42 screen , what time should I enter, say they have taken 4 hrs to complete the work.How the cost will come .Please, explain .thanks in advance.

rdgs

rajib

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

you have to specify the Calculation key as calculate work ,then you have to enter the operation duration as 3 and number 4 then you can get the work duration 12 .

or you have to enter work duration as 12 and number 3 then operation duration is 4

formula is work dur/number = Operation duration

regards

thyagarajan

MTerence
Active Contributor
0 Kudos

hi

You can also maintain in header data CCkey as "Calculate Duration"

In operation

Enter Work Duration ( 4 X 3 = 12)

No of capacities - 3

Then u will get the actual duration as 4 hrs for each

Former Member
0 Kudos

Hi:

I didn't get your answer, I think the Cost will be calculated based on the work duration X Activty rate/hour right?

Former Member
0 Kudos

HI,

The actual cost calculated based on the confirmed wrok time

Yasser

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

thanks to everybody

rgds

rajib