on 09-15-2008 11:49 AM
Hi everybody
I have problem with Inbound Delivery
- I created PO with confirmation control key = ANLI.
- After that I created Inbound Delivery refer to PO.
- When I post GR, system says there is no item selected.
- I go back to Inbound and see that Pick qty = 0.
- I tried to create TO to pick full quantity but error msg:
An internal error has occurred (L03T 0154 H )
Message no. L3705
Diagnosis
No screen sequence control is defined for the argument enclosed in parentheses in the error message.
Procedure
Contact your system administrator about this error. Note down the parameters in the error message and the situation that caused the error.
Do you know what i have to do to fix this problem?
No body help?
I have tried to create other PO with other Vendor - same material. After create DO, it auto fully pick, then i can process GR,
I think the problem is Vendor. I create new Vendor by copied from that Vendor but DO still have the same problem. do you know what i have to check for this case?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.