Back flush mandatory

Former Member
0 Kudos

Dear PP Gurus,

1. I want to make backflush indicator mandatory in production order. Sometimes while creating master data, the user forgets to put Backflush indicator.

When we do confirmation, that material which do not have backflush indicator is left out to be issued.

So If we make it mandatory in work order , this can be avoided.

2. Can we make goods movement for all materials automatic whether backflush indicator is ON or not>

Thanks & Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

U can do this through config setting also. In OPK4 for the order type u tick on All components under Goods movenent option. So when u confirm with this order type system will do auto GI.

Pls check & revert back.

Edited by: BNR on Sep 15, 2008 1:02 PM

Answers (5)

Answers (5)

Former Member
0 Kudos

Thanks, I am closing this thread

Former Member
0 Kudos

Hi Shalini

If the problem is not solved, then pls revert back with the issue or else close the thread by rewarding.

Thanks & Regds

Former Member
0 Kudos

HI

1.you can give back flush indicator in material master, MRPview 2 (always backflush)

2. and in IMG you have option OPK4 goods movement check box all components, if you tick this all the componets in order will come to confirmation goods movement(without master data backflush seting)

-ashok

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

You can set Backflush Indicator in

- Material Master

- Routing / Master Recipe

- Work Center.

Depending on the above settings in one of the Master data,components are backflushed automatically during order creation.

Now if you are using MRP profile for Material Master creation then make tick active in profile itself.

Regards,

Dhaval

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

You can maintain the backflush are as,

1)Routing

2)Material master -MRP-2 view -1Always Backflush, 2-Depend On work center.

3)Work Center-It depend on material master.

Or in OPK4 for your order type nad plant select tick mark as all componenet.

Regards,

R.Brahmankar