Hallo ,

Case : Changes are made to "X" Material.

The Changes after saving are reflected in Change history .

The same changes are not reflected in the Material itself.

Could anyone let me know under what circumstances the system behaves like this ?

Regards

Ramesh Ch

Accepted Solutions (0)

Answers (2)

Answers (2)

csaba_szommer
Active Contributor
0 Kudos

Hi,

Please be more specific. What's your problem exactly?

- you can example carry out a change using MM12 and the result will be seen later

- are you checking the material using proper organisational levels?

- have you checked the related data tables (mara, marc, mbew, etc)?

Please give more details.

Thanks,

Csaba

Former Member
0 Kudos

Hi ,

The Changes are made to the Material "X" in the views MRP1, mrp2,mrp3 and mrp4.

These changes are related to Pur.Grp , Mrp Controller, Mrp Type, Availability Type etc.

The Change Log is visible in the Transaction mm04 .

Please note these changes are finally not visible on the screen where the changes were done initially but only the log is visible.

If you have any queries , please revert back.

Regards

Ramesh

csaba_szommer
Active Contributor
0 Kudos

Thanks for the info, but please answer the three points posted in my previous message.

One more: in which system you are? (I checked OSS notes 385043, 382311 but your problem seems different from these)

Edited by: Csaba Szommer on Sep 15, 2008 1:38 PM

Edited by: Csaba Szommer on Sep 15, 2008 1:46 PM

former_member190537
Active Contributor
0 Kudos

Hello,

Plz check material changes are get in from T.code MM04

or else go to MM02 and Check Goto Menu bar-> Environment-Disply changes

You will get the results

Mahesh Naik