HI Sapguru,
I have one typical scenario,
In my clients cement business process there is a variations in bom materials by % at regular intervals.It is nota fixed bom. Based on the feed back of Quality controls, they need to create the BOM for that material.How to map this scenario in sap.
If not any other method please do needful and give me some idea.
Regards,
seenu
Hi,
For this kind of % change If you have fixed variation or variable variation. You can use the concept of MQC (Material Quantity calculation). Are you using BOM or Recipie?
If it is process industry. please follow the following path to understand the MQC concept.
SAP help Path--
Production Planning - Process Industries (PP-PI)--->
Process Orders --->
Material List Components -
>
Material Quantity calculation
Revert back
Thanks & Regards
Kundan Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think BOM has not to be created every time, even I don't think you should change the quantities of components in the BOM, you shoudl maintain an average qty for each part.
If the consumed quantities always vary, you should change the component list of the PrdOrd or the quantities of components at the time of confirmation.
Csaba
Edited by: Csaba Szommer on Sep 15, 2008 11:49 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.