I am having problem as Account Assignment Catagory P,Q in assigning material to project.When i create PR,Through ME51N then in case of Q(Project make to order)
commitment value is not shown in any commitment report.
After consumption (GI) its showing.
But in case of service AAc P,Item Cat. D commitment value is in commitment report.
In Q consumption Posting is P but in case of P its V.
When i Changed In P to V not any effect.
I've check the account Ass Catagory in SPRO .But its seems to be OK.
Is requirment Class is responsible for this commitment value .
regards.
The GL account code that is being determined in procurement for the material should be created as 'statistical cost element'. Ask FI person to create this. Once this is done, you will automatically see commitment value. This is as per standard SAP. In case yoiu do not get this value as commitment, please rebuild PS infor data base once using transaction CJEN.
I hope this helps to resolve your issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ask him whether he can create Cost Element for Balance sheet accounts. He will say no. But tell him for the budget availability control as well as showing commitment value in project reports, SAP has provided a feature of creating stastical cost element for these accounts. These are category 90. I am talking from my experience, I have already faced with this situation and I got the same answer from FI person. Finally after lot of argument, I got this done. Needless to mention, I expected this reply from your FI person as well.
Run transaction CJEN, remove check box against 'test run' and 'background execution' and execute the transaction. This rebuilds the info data base in case there are some misses. Once this is done, you should be able to see value in commitment. Even after this you do not see value, please carryout new purchase for the same material. Commitment value has to appear.
I have to find out why it is not showing value against network activity. Check whether it is showing actual value against the activity after posting. It should show against activity. Check the PO, what is it showing in account assignment tab, does it show network activity or the WBS Element. Values will appear as per the account assignment.
For processes of CJEN, please another message, I will explain to you what is it all about.
Q is used for project stock which is not committed to the WBS, this will appear only after consumption as you have observed
If you are not using project stock functionality then do not use this for account assignment of WBS for PR etc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.