MRP Run scenario

Hey Guys,

The scenario is somethng like this....

I have two Purchase orders in a plant. When i run the MRP I get only one planned order. The planned order is created for the total quantity of the two purchase orders combined.

My question is:

1)Is it natural for the system to throw only one planned order and if so why?

2)If I have a PIR and I run the MRP i get individual Planned orders for each PIR. Is it possible to get individual Planned orders for the above scenario i.e. for each purchase order in the MD04 screen i need a planned order to be generated.

Regards.

Srinivasan R