I have a question here reg. automate cost calculation.
For this, I have created Req. Class, Req. Type, assigned req type to req. class, assign item cat. to req type and costing has assigned to req class.
Here the question is.........
- In req. class(TC:OVZG) under Assembly tab there is a assembly type, order type... what is the useful of these fields and what's control? In req class, client wants to fill in assembly type as "2" or "0"
- In req. class under Account Assignment tab there is a settlement profile....what is the useful of this filed and what's control? In req class, client wants to fill in order type as "PPC1".
Is there any link with these fileds to automate cost calculation.
Looking forward your valuable thoughts/ideas....
adv thanks
vk
We are not using any assembly type or order type in MTO scenario for our requirements class (transaction OVZG).
Settlement profile is required to settle the order. After the production process is completed the order needs to be settled so that costs are settled and for this reason a settlement profile is required. Costing variant PPC4 should be used in make to order scenario.
Regards,
GSL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.