on 09-15-2008 7:55 AM
Hii Gurus
Client has created PM Plan to generate a PM order for every 500 Hrs or 120 Days based on the last completed PM Work Order.
The plan has a Call 1 which is having the Reference Date was set to the 23.07.2008 and an Hour Meter reading of 1500 Hours was recorded at this time. (Via Notification linked to this Work Order)
Since then no further Hour Meters have been recorded and under this scenario, then system would then refer to the Annual Hour Estimate to determine if the Service should be due on hours or days depending on which comes first?
If I am right in this assumption then I can see that the Annual Hour Estimate for the Equipment linked to this plan is 1500 Hours which then should indicate that the truck on average works 4.1 Hours a day (1500/365) and hence would require 120 days to be due again. The system has made the next PM Plan due on the 21.09.08 which is 60 days from the last PM Work Order which I cannot understand why?
If any one could explain me why the system has generated it after 245 days is greatly appriciated.
Can you confirm please is it required to post at least one measuring document against the counter after scheduling of Multiple counter plan for proper working of plan??
Dear All
We are closing the issue as we have resolved the issue by programatically. Thanks for your all replies.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
can you specify when you have scheduled the maintenance plan and the initial counter reading for start of cycle .
Also system will calculate the planned date based on Annual estimate and current counter reading .system will adjust the dates based on the current performance
kindly refer the following [link|http://help.sap.com/saphelp_erp60_sp/helpdata/en/3c/abb413413911d1893d0000e8323c4f/content.htm]
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
See the customer has scheduled the plan on 07.07.2006. In that plan he is having only two counter one is Day (Time based- Automatically counted & not required to update reading). Hour Meter for Truck(Needs updation through Measurement documents). intial counter reading was 0 & he has not entered single reading against the second counter.
According to him system should consider the Annual estimation reading for deciding next planing date which is righit.
I have conducted two trials
1. Created plan like him. Scheduled but not entered any reading. The plan is giving same problem during processing.
2. Created plan like him, Scheduled & posted one measurement document after scheduling of it. The checked & found that the pproblem is solved & that plan is not giving any error for premature scheduling.
So My question is there a need of posting at least a single measurment reading document on counter after scheduling of that plan?
Regards
Makarand Gurjar
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.