on 09-15-2008 7:30 AM
Hi All,
My client has a requirement. They want that approver can change the PO duting the approval process at all levels of release. Curently only the first level approver can change the PO. Is this a standard SAP functionality ? If PO can be changed at all levels, than please help me...\
Regards,
Satyendra
hi
consult with ur basis person for authorization for the person
regards
kunal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Changes After the Start of the Release Procedure have the following impact.
The following cases can arise when a purchase requisition or external purchasing document (PO, etc.) for which the release procedure has already started is changed:
Case 1: Insignificant change that does not necessitate a different release strategy.
Case 2: Relevant change that does not necessitate a different release strategy.
Case 3: Relevant change that necessitates a different release strategy
In each case, the system issues a message to the user after the change has been made. So. there can be upto 8 (max) users, who can do the changes to PO (you will control through authorizations, for whom you want to give "Change" access) .
Only thing is, you have to consider the above 3 cases in Releasing that PO.
Regards,
Narayana.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use changable value from 1 to 6 in release code for all release indicator.
Rgds
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use release indicator 6.
Regrds,
Raviraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.