Migo changes

Dear SAP Friends,

I had doing MIGO for material X,But I forget to take the Excise duty on that.

The material goes in Quality,there it is Accepted(UD) & send for the unrestricted use for further process.

Now I want to do the cancellation of MIGO.For that I had already cancel the QM activity.Material is now transfer from unrestricted use to QM location.

when i do cancellation of MIGO,it gives the error message that"GR Can not be canceled as QM lot is partly process".

Then How can I add the excise duty in that MIGO?

Please Reply.

Regards,

Chandra.

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question