What's the usage&influences of the factory calendar in the project profile?
Is that relating to scheduling? If so,how?
In our project the factory calendar is W8(every day is working day), but when i schedule on the network,i don't see any influence(weekends are automatically subtracted).
regards,
tiger wu
check the factory calendar for the work centre used on the networks, this could be different from W8 - the scheduling is based on the factory calendar of the work centre
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tiger
In project profile, it uniquely identifies the factory calendar valid for the plant. It is defined on the basis of a public holiday calender.
Scheduling uses the factory calendar in the work center if you have entered a calendar in the work center. Scheduling uses the factory calendar in the activity or relationship if you have not entered a calendar in the work center
Scheduling uses the factory calendar for the plant only if you have not entered a calendar in the work center or activity.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.