any standard Repot person assignment , wbs wise

Former Member
0 Kudos

hi PS experts,

cn u pls. suggest any standard repot which will give the details of project expenditure wbs and person assignment wise.

thnx in adv.

regards

ashis

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Try below report:

S_ALR_87100190 - Plan/Actual/Variance for Each Project and Person Responsible

Regards

Sreenivas

Former Member
0 Kudos

hi Sri,

i chkd dat report its form is 3CST6.

dere also i dd nt find the project team option.

cn u pls. suggest any other report.

Former Member
0 Kudos

Hi,

try out CJI3 which gives you actual cost for a given project.