on 09-13-2008 8:27 PM
i heard that by using production version we can select the bom and routing. when do we select these?
when creating a production order. and where do we select routing in production version. I didnt find it any where.
Hello,
Your are right , you can select the Routing and BOM using the production Version while creating the Production order manually . (CO01).
Please follow below steps,
1. Assign the routing Group number , Group counter number and Alternate BOM number at Production version .
2. Assign the BOM selection method = 2 & 3 ( by production version ) at MRP view of material.
3. Set the production version selection = manual for order type/'plant combination at OPL8.
Now create production order system give popup t o select the PV.
Please try and close the thread by rewarding point if you found usefull
Regards
Pradeep kumar
Edited by: Pradeep Kumar on Sep 14, 2008 1:09 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.