Hi SAP Gurus,

We have around 5000 cost centers and 6000 cost elements for which "Valid to" date is 09/27/2008. We need to extend this date for another 5 years.

Can you please suggest any pointers as how we can do the mass update.

We have already tried KS12 which is not of any help.

Thanks,

Sreeni.

1-408-307-7965

CA, USA.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sreeni,

You can use LSMW.

e.g. you cost center current year end is 12/31/08.

using LSMW you can create same cost center from 01/01/2009 to 12/31/2014.

Hope this helps you.

Thanks,

Rau

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Run the LSMW.

Or Use the fuction automatic creation of Primary/Secondary cost elements in the SPRO.

Or You can write a program which replaces the valid to date directly in the database table.

For this you require ABAPER help.

Regards,