on 09-12-2008 6:37 PM
Hi,
We are currently on ECC6.0.
We have a problem with IW31 BDC being called in a custom program using CALL transaction.
When we click on the Basic start date F4 for the first time in the day, the factory calendar appears for a split second and disappears, and defaults the Basic Start date to the current date. All dates further work properly in terms of the calendar pop-up.
This problem occurs in the following scenarios inconsistently -
1) for the first time in the day when u logon to the system
2) soemtimes, every fresh login to the system.
In case any of you faced this problem before, let me know.
TIA...
Regards
Deepthi
Dear Deepthi,
I request you to please raise this thread [here|https://www.sdn.sap.com/irj/sdn/forums]
This issue look like an ABAP development.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.