Process Order delivered quantity reduction after UD (321 or 309 mvnt)

Hello All,

I have a following business scenario :-

An Insp lot (04) is generated after a GR against a Process Order for every batch, while making UD i can post the quantity to new material.

Problem :-

In the order i already have the 'Delivered quantity' when I make the GR (101 mvnt) say for e.g 100 kg and I have 2 batches of 80 & 20 kg with two inspection lot open say A & B

With the inspection lot B I can post the 20 kg quantity to a new material.

But when I post to the new material the 'Delivered Quantity' in the order is not reduced accordingly which is creating problem. It remains 100 kg and its expected to get reduced to 80 kg as i have posted 20 kg against the new material.

Is there any OSS note which fixes this issue or do you know the workaround ???

Thanks in Advance

jagdish