to consider subcontract stock during mrp run

0 Kudos

Dear all,

while mrp run it is not considering subcontractor stock .Is there any setting in spro so that it will consider subcontractor stock into consideration.

with regards

cp vijaya kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

No as it is a special stock (o) in normal MRP unless yiou go for MRP area with subcontract as vendor MRP area.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Special stocks are not considered for MRP run. Subcontracting stock is a special stock(O), hence is not considered for MRP.

Hope clear to you.

Regards,

R.Brahmankar