Hi!

We transport currently all transports with u201EIMPORT ALLu201Cmethod and are thinking about the implementation of ChaRM.

This method (u201CIMPORT ALLu201D) allows us to transport the transports at 10 and 14 ou2019clock automatically from DEV into QAS system

As we know ChaRM works with SINLGE IMPORT method (CTC=1).

Questions

1) Do we have any possibilities for the automatic transport in ChaRM?

If Yes, how does it work?

2) Do we have any possibilities for locking of objects and mechanisms to avoid "outrun of transportsu201D?

Developer 1 works with objects A, B, C, changes the object B and transports them into QAS system.

Developer 2 works with objects B, G, H, transports the object B into QAS system.

Now he has the other version of object B, because the object B was changed by developer A.

Does ChaRM offer some mechanisms to avoid u201Coutrun of transportsu201D?

Any helpful information will be very appreciated and awarded with points.

Thank you very much!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

1. Look at note 1897163

2. Downgrade protection within ChaRM

Thanks