How to close a project.

Former Member
0 Kudos

hi

Can anyone expalin how can a project can be closed as when I am trying to close one project, i am not able to do because of some blocked invoices.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

nice

come on

former_member348872
Active Contributor
0 Kudos

What is the Error message ?

How closing is related to Blocked invoices ?

Ideally you should be able to close projects by CJ02 / CJ20 / CJ12. - Menu - Edit - Close.

Former Member
0 Kudos

Hi

The error message is 'Status cannot be closed;blocked invoicex exist' . When I checked the in "Status w/o status no." there check box for Lock Budget is selected. If I uncheck this box and select the radio button for Close, then I am able to close the project. But there are already some project existing which are having the check box for Lock budget as unchecked but still status of that project is appearing as CLOSE BLOCKED.

IInd issue is that, If I do change the status to CLOSE as mentioned above, I am able to do that successfully. But If I try to close the project from Edit-> status-> close, I am not able to do and I am getting the above mentioned error message. Is there any validation that is triggering here.