Hi Gurus,

In qty reconcillation for subcontracting items in j1ifq, user is getting error " excise document is posted later to material document" message no.81576.Pls help

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In Sc scenarios, u have to reconcile the quantity after the GRn has done, since the qty wt u send & wt u received may be different at the time of GRN & u r trying to reconcile this error will be coming.

through 542 get the remaining qty from the Sc vendor, then do Reconcile in J1IFQ

Pandari

Answers (3)

Answers (3)

deiva
Active Contributor
0 Kudos

Hai,

1.You do the reconcillation of subcontracting challan by J1IFQ with ref to material doc created by 101 mvt type & enter the Sc Challan also.

2.The reconcillation date should be as same as the GR date. Check the same.

kunal_ingale
Active Contributor
0 Kudos

hi

hope u have followed process as follows

  • Purchase order creation based on a scheduled purchase requisition created by last MRP run ME21N

  • Components of the Material sent to the subcontractor through a Transfer Posting migo > 541

  • Creation of Subcontracting Challan J1IF01

  • Goods receipt for purchase order delivered by subcontractor MIGO

  • Reconciliation of Challan J1IFQ

  • Completion of Challan J1IF13

  • Invoice verification and validation of tax expenses MIRO

  • Outgoing payment

http://help.sap.com/bestpractices/BBLibrary/HTML/J75_ThirdPartyOrdProcwithSub_EN_KO.htm

REGRDS

KUNAL

Former Member
0 Kudos

Hi,

Can you tell me what all are the transaction you posted in sequence ?

Based on this we can suggest some thing.

reg

Durga