assign activity to cost senter(product costing)

Former Member
0 Kudos

dear all,

could anybody sugg me, where we have to assign costcenter to activity type,becz while creating (create cost estimate with quantity structure)CK11N when iam saving the data then error displaying is assign cost center to activity type.

regards

usha rani.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Usha Rani, You need to enter planned price against the Cost Center and the activity type in KP26. Trust this helps much! Cheers, Ashok SINGH

srinivasa_maruvada
Active Contributor
0 Kudos

Hi

Use TCode KP26 and check KP06 to have a greater idea

Cheers

Srinivas