on 09-12-2008 5:48 AM
Commmited Delivery Date in Purchase Order?
Can any one tell me , how is the commited delivery date in Purchase Order Determined!
I get a date which is sunday as committed delivery date but according to Route Calendar and shipping
point calendar sunday is not a working day?
Any suggestions?
Thanks!
Hi Kumar,
That committed date automatically defined by system while creating the delivery for that PO item.
But if you can't see any delivery for that PO item, that means the created delivery has been already deleted. Also you can see delivery committed qty within next columns under "Delivery Schedule"
But unfortunately you cannot find that deleted delivery or any other information regarding that delivery number!
Regards,
Charith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
find this notes might be use full for you .
Commitment dates switch for calculation rule
Key that controls how the commitment quantities should be calculated per sales document type.
Use
The commitment date is calculated using the delivery time for releases to contracts with delivery times, or sales orders that refer to quotations containing delivery times. The committed quantity results from the agreed delivery time or the confirmed quantity, according to the calculation rule set here.
Dependencies
You can set the following calculation rules:
A: Consider agreed delivery time
Here, all required schedule lines are committed for the date that lies at the agreed distance from the delivery time, according to the date on which the order was placed. If the customer requests a later date, this can be confirmed. The confirmation does not affect the calculation. If you do not enter a delivery time, the system does not calculate a committed quantity.
B: First confirmation date
The committed quantity is calculated according to the first confirmed quantities. If a delivery time exists for the item, the system takes it into account, as in calculation rule A, and confirms the earlier date. The commitment date is recalculated if the material, quantity, first date, or delivery time change. The quantities confirmed then are valid once the document has been saved.
C: First confirmation date
Rule C is the same as calculation rule B but for new items. If you save a document again but the system can confirm more for the customer, the more favorable situation will be saved as the commitment. As in rule B, the commitment date will be recalculated if changes are made to the material, quantity, requested delivery date, or delivery time.
No entry
Commitment dates are not calculated or displayed.
With best Regards,
venkataswamy.y
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.