on 09-12-2008 5:11 AM
We have made some changes on the material master ( ie storage location), How can I update existing released production orders ( no confirmations carried out ) so that they reflect these changes on the prod. orders and avoid error during confirmations?
Thanks,
BB
hi
goto Co02 and clcik on master data tab, ther you can see the prodcution version filed, click on flower button, to read the master data.
or in menu goto functions-->clcik on Read PP master data.
-pltry
ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In change order tcode, goto Functions->Read PP master data.
Confirm the pop-ups, system will change the status of order to CRTD. Further make reqd changes and release the order. Please note that any changes made directly in order other than in routing will be lost during this transaction.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.