Dear All,

I setting up the sub contracting in APO SNP, this is the list of what I have done

Location 0000142477 Location type 1011 Vendor as CIF from R3, this is a sub contract location for me

Location AU20 Location type 1001 production as CIF from R3, this is my Plant

Created Product 52864094, for both Location and procurement type F (Special Procurement 30 in R3)

PPM for 52864094, CIF up from R3 as type P and Generate SNP PPM, Type S

Transportation lane Start loc 0000142477, to Destination Au20 with the Sub contracting purchase Info record

All the raw material from the AU20 to 0000142477

Seem pretty much all my Master data are completed

My problem is that in the Planning book 9ASNPSBC, material 52864094 in location AU20 I have demand, I execute the Multilevel heuristic, which in Theory, it should create the Purchase requisition in AU20, type subcontract and then some kind of plan production in 0000142477, but actually Nothing Happen, no Purchase req suggest for Both location

Vice versa, If I execute Heuristic run for this prodduct in AU20 form PP/DS, I got Correctly Purchase req in both locations,

Do I missing something in SNP ???

Could you guys give me a hint on this

Thanks and best regards,

Kittichai