on 09-12-2008 3:52 AM
Hi there,
In transportation module, while creating shipment cost document, business area is not flowing automatically. Upon more exploration we found that plant is also not flowing, and may be because of that business area is not flowing. What can the posible reasons for plnt not flowing? Suggest solution.
Thanks and Regards,
Deepshikha
Dear Deepshikha,
Please check the Assign purchasing data settings in T_53 transaction with the combination of the plant.
Through this setting plant will flow in the shipment cost document.
I don't have idea about where the businees area field avail in the shipment cost document.
If so please chek the settings related to business area through this IMG path.
SPRO>IMG>Enterprise structure>Assignment>Business Area Account Assignment.
Define Rules By Sales Area
If Rule 1 is assigned then
Assign Business Area To Plant And Division
If Rule 2 is assigned then
Assign Business Area by Sales Area.
I hope it will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.