Converting Planning file

Former Member
0 Kudos

Hi

I have to configure MRP area for this I need to convert the existing planning file (table MDVM) to new planning file (table DBVM).. when I execute this will there be any impact on the existing MRP process? we have not used MRP area till now.

Please get back to me....

Jade

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

There will no impect impact on the existing MRP process.

In Material master record in MRP 1 view , MRP view tab will be seen but only after you convert planning file entries.

Please refer this link,

[Converting Planning file|https://forums.sdn.sap.com/click.jspa?searchID=16205768&messageID=5780960]

Regards,

R.Brahmankar