Maintain Validity Date for Mitigation Control Assignment to Users Virsa 5.2

Former Member
0 Kudos

We have over 1,000 SoD's all mitigated. The val;idity date for these mitigation controls needs to be updated. Does anyone know a way to perform a range of updates so it is not necessary to update each user assigned to a Mitigation Control.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Currently there is no way you can make mass changes. Just download the informationa from backend and upload that with the changes. Take help from Basis guys to perform this task.

Thanks,

Tavi

koehntopp
Product and Topic Expert
Product and Topic Expert
0 Kudos

The only way to do that currently would be to download the table information, edit in Excel and re-upload the table.

Not for the faint of heart, but doable.

Frank.