MD04 reading

Hi All,

Could you please let me know as how to read MD04 List. I am quite confused. For ex :

Material :12345678

Date MRP Element-MRP Element Data-- Rec/Req Data-- Available Data

10.09 Stock 0

10.09 PrjSt A-B-C-D

10.09 PldPrd XXXX 2 2

10.09 OrdRes XXXX 2- 2-

10.09 OrdRes YYYY 1- 0

10.09 OrdRes ZZZZ 2- 2-

The requirements (or reservations) are coming from projects.

Please reply. Mainly I want to know what this negative or positive value means in case of Ord reservation, Pld order, Prd Order etc..

Kindly read the values in respective columns according to

Date MRP Element-MRP Element Data-- Rec/Req Data-- Available Data

Thanks in advance.

Cheers

Sunny

Former Member
Former Member replied

Dear,

Planned order is a receipt and is always +ve. OrdRes is a type of requirement and will be -ve. the first line is stock line and will be +ve always.

Hence system will do the calculation as below

Stock + receipt like pl order - requirement like order reservation and see the net requirementa nd when you run MRP will cereate required recipt so that net is always zero.

In your case for each project segment system will do the above calculation and see that project segment net qty is zero after MRP run.

pl come bakc if required