Hello Gurus,
We use Component scrap in our BOMs.
MRP calculates the requirements including the scrap and that is fine. Is there a way that when we create production/process orders the components' required quantity will not include the scrap automatically? We don't want the components to be issued with the additional scrap, but rather issue the scrap by request only if required.
Thanks
Not possible.
The SAP logic is tht procurement of RM and Production & consumption has to be in line. Functionally tht is ideal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I do noth think this facility is avaialble in Discrete/PP-PI.
It is avaialble in REM.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.