on 09-11-2008 1:05 PM
Hi,
In CAT2 I enter time against Activity Type and WBS Elment. When I run the CADO report, I get the Sender Cost Center as the one maintained in PA30 (IT-1). But I dont understand where does the receiver Cost center gets picked from. Please help!
Regards,
Remya.
Hi,
Check if system is picking 'Resp. cost cntr' or 'Req.cost center' from 'Basic data' tab page of WBS in CJ20N. Also the WBS is statistical, system may be picking actual cost object from 'CCtr post.' on Control tab of WBS in CJ20N.
Regards