on 09-11-2008 12:27 PM
Dear Gurus,
Can we take a report on % completion of activities?
Suppose network have 10 activities under different WBS, then can the report be run showing % completion status of all activities.
And can the similar report be obtained for texts mentioned in the activities?
Dear,
You should use the T code CNE5 and select the N/W or WBSE OR Project then run the report and select the % work ,remaining work .
Try this .
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
U can go thru CN47N prior to which u need to put confirmation % for the activities
Rgds