How to excluse some materials for reminder sending

Hi,

In SAP we can set up at material level when POs for that certain material are relevant for reminders. If we set 0 days, then the PO for that material is immediately after the delivery date reminder relevant. How can we exclude material for reminders? Meaning: how can we set up the material master in order that POs for that certain material are never relevant for reminder letters?

Thx,

Peter

replied

Dear,

You create purchase value key for reminders using the following:

SPRO u2013 Material Management u2013 Purchasing u2013 Define purchasing value keys

and

in Material master you define this key to material record to activate reminder/expeditors.

Just simply remove this value key definition from material master if previously assigned. If not leave it blank, so for this material are not relevant for reminder/expeditors.

Regards,

Syed Hussain.