on 09-11-2008 11:09 AM
Hi,
i have entered a budget (input planning) with Tcode KP06, i show it by Tcode : S_ALR_87013611 but not with Tcode : KE80
Please why this budget is not displayed by KE80 ? is there any configuration to do for that ?
Please help
Regards.
Hi,
KP06 is used to enter planning for cost centres, while KE80 is a transaction for PCA reporting. So, it should not show you the planning for cost centres. If you want to plan for profit centres, use other transactions.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, but there is a relation between costs centers and profit centers : When we create a new Cost center (KS01) we must enter a profit center, therefore any information concerning a cost center must be anlyzed in profit center reports. if not, why we enter a profit center in a cost center master data ?
1) Our controller has upload the cost center budget for year 2014, now manager asked me to get the extract of the cost center budget from SAP
2) How we can find out that if the the profit center budget has been uploaded in sap or not.
if so by which report we can extract the data.
Best Regards
Hi Fatima,
1. You can extract the Cost Center Planning from Standard Reports s_alr_87013611.
2. If new GL is implemented and Profit Center Planning is uploaded using T.code: GP12N then it will reflect in report S_E38_98000088 - Profit Center Group: Plan/Actual/Variance
If Profit Center Planning is done using T.code: 7KE1 tgghen it will reflect in report S_ALR_87013326 - Profit Center Group: Plan/Actual/Variance .
Regards
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.