Problem with MRP for material with lot size of multiple months

Hi Gurus,

I'm running MRP for a material where i have a lot size withLotSizeProced. P Period lot-sizing proce

Lot-size ind. M Monthly lot size

Scheduling 1 Period start := deliver

No. of periods 10

When I run MRP i get error

30.06.2011 date comes after end of valid factory calendar. (Please correct)

Any idea?