Hi,

Is it possible to map below scenario in SAP.

Reorder point set at 100 kg for material ROH, and safety stock level maintained 40 kg, now when stock comes to below the reorder point say 90 kg that time system should create Purchase Requisition for 10 Kg without MRP Run.

Please revert if possible it to map.

Thanks in advance,

Vishal

replied

Hi,

Please refer this link,

[Background Jobs for MRP |http://www.sap-img.com/pp019.htm]

[Thread.|Background MRP;

Regards,

R.Brahmankar

Edited by: R Brahmankar on Sep 11, 2008 2:53 PM